Nuclear energy is undoubtedly most controversial, yet critical part for India's future energy security. As we know India's annual energy demand is expected to rise to 800 GW by 2032, it is very important to consider every source of energy in the optimum energy mix. Arguments in favor of nuclear energy become even more compelling if we consider vast thorium reserves that India have. Yet there are strong and reasonable apprehensions against use of nuclear energy which can't be ignored. Stress can be laid on cautious development, safety precautions in operations and disposal of wastes through continuous innovations, and also on minimization of waste generation. But development of nuclear energy can't be stonewalled because of such concerns.
India Nuclear Program has roots in establishment of Tata Institute of Fundamental Research in 1945 with initiative Dr. H. Bhabha. It undertook research in nuclear physics and cosmic rays. In 1948 Atomic Energy Commission was constituted to work for Indian Nuclear Program. Main area of commission was prospection of nuclear raw material resources of the country. India has insufficient Uranium reserves of 1-2% of global reserves, but is endowed with one of the largest reserves of Thorium which constitute about 30 % of global reserves.
Thorium however is not fissile and can't be used directly to trigger Nuclear Reaction. But it is 'fertile' and what makes it Nuclear Fuel is the fact that its isotope Thorium – 232 can be converted to Uranium -233 which is 'fissile'. This process of conversion is called 'Transmutation'. To exploit Thorium reserves Dr. Homi Jehangir Bhabha conceived '3 Stage Nuclear Program' which is explained below.
1st stage of Nuclear Program –
Reactor Used – Pressurized Heavy Water Reactor
Fuel Used – Uranium
Moderator and Coolant – Heavy water and Light water
Uranium in its natural form consists of .7 % of isotope Uranium-235 which is fissile. Remaining 99.7 % consist of Uranium – 238 which is 'Fertile' not fissile. Uranium is generally enriched before put to use by which proportion of U-235 increases in comparison to U-238. When Nuclear reaction takes place Neutron is bombarded on nuclei. This splits the atom in 2 parts (sometimes 3 parts) and releases significant amount of energy. Along with these 3 neutrons gets released which collides and splits some other U-235 nuclei; this is what results in 'self-sustaining chain reaction'. As we can see neutrons released (3 per fission) are more than neutrons consumed (1 per fission), overtime there are surplus neutrons after the chain of reactions.
Some of these surplus neutrons get absorbed in other isotope U-238 (which forms 99.7 % of uranium) to give plutonium (Pu- 239), which is 'fissile' (by transmutation).
As a result spent fuel of at first stage consists of Pu-239 and significant amount of U-238 which didn't get any Neutron to get converted in plutonium. This fuel then goes to 2nd Stage which consists of Fast Breeder reactor.
Why heavy Water is used? – It Moderates the speed of Neutrons released from reaction. So that its probability of fission with U-235 is increased significantly.
2nd Stage of Nuclear Program
Reactor Used – Fast breeder Reactor
Fuel – Mixture of Uranium-238 and Plutonium-239
No Moderator is needed
Sodium is used as coolant
Pu-239 is a fissile material and on reaction this too results in extra neutrons than current chain reaction needs. These extra neutrons again are absorbed by U-238 and converted to Pu-239. At this stage more fuel is generated than is consumed. That is why it is called 'Breeder reactor'.
This reactor doesn't use Moderator as at high speed of neutrons only, does Pu-239 produces extra neutrons.
Further, 2nd stage is crucial for 3rs stage as it will convert Thorium-232 (which occurs naturally) into Uranium – 233 by transmutation. This will be done in following way –
Once sufficient Power Generation capacity is achieved at 2nd stage and there will be good reserves of Pu-239, then Th-232 will be introduced at the periphery of the core(blanket material) fuel which will be Pu-239 alone (instead of present mixture of Pu-239 & U-238). This while core fuel will be consumed and extra neutrons will be created. Again, Th-232 will get converted in U-233.
In 3rd stage of nuclear program, again Th-232 will be at periphery of Core fuel i.e. U-233, which further will result in U-233 fuel.
The AHWR is another innovative concept, which will act as a bridge between the first and third stage essentially to advance thorium utilization without undergoing second stage of the three stage program. It uses light water as coolant and heavy water as moderator. It is fuelled by a mixture of Pu239 and Th232 with a sizeable amount of power coming from Thorium 232
.
Thorium is said to be more efficient and gives less radioactive waste than Uranium and plutonium. Also, plutonium can be separated from waste and can be used to make bombs. This is not possible with Thorium.
Progress so far
Power station
|
Operator
|
State
|
Type
|
Units
|
Total capacity (Netto, MW)
|
|
|
|
|
202 x 4
|
808
|
|
|
|
|
202 x 2
|
404
|
|
|
|
|
205 x 2
|
410
|
|
|
|
|
202 x 2
|
404
|
|
|
|
|
90 x 1 187 x 1 202 x 4
|
1085
|
|
|
|
|
150 x 2 490 x 2
|
1280
|
|
|
|
|
917 x 1
|
|
| | |
Total
|
21
|
5308
|
The projects under construction are:
Power station
|
Operator
|
State
|
Type
|
Units
|
Total capacity (Netto, MW)
|
Expected Commercial Operation
|
|
|
|
|
470 x 1
|
470
|
March 2015
|
|
|
|
|
630 x 2
|
1260
|
Unit 3: 2015 June, Unit 4: 2015 December
|
|
|
|
|
630 x 2
|
1260
|
Unit 7: 2016 June, Unit 8: 2016 December
|
|
|
|
|
1000 x 1
|
1000
|
2014 December
|
| | |
Total
|
6
|
3907
| |
The planned projects are:
Power station
|
Operator
|
State
|
Type
|
Units
|
Total capacity (Netto, MW)
|
|
|
|
|
630 x 4
|
|
Chutka
|
|
|
|
630 x 2
|
1,260
|
|
|
|
|
630 x 2
|
1,260
|
|
|
|
|
630 x 2
|
1,260
|
|
|
|
FBR(Fast breeder reactor)
|
470 x 2
|
940
|
Site to be decided
| | |
|
300 x 1
|
300
|
| |
|
|
917 x 2
|
1834
|
| |
|
|
1650 x 6
|
9900
|
| |
|
|
1594 x 6
|
|
| |
|
|
1100 x 6
|
|
| | |
Total
|
33
|
34498
|
Source: Wikipedia
1st Stage of Program is undertaken by Nuclear Power Corporation of India Ltd whereas 2nd stage is under Bharatiya Nabhikiya Vidyut Nigam Ltd. (Bhavini) for Fast Breeder reactors.
India has now capacity to build completely indigenous Pressurized Heavy Water Reactors
These are supported mainly by two research centers – Bhabha Atomic Research Center and Indira Gandhi Centre for Atomic Research .
1st two reactors were at Tarapore, in Maharashtra. These were of 'Boiling water type' and were not part of 3 stage Nuclear program. These were American reactors supplied General Electricals . Later in late 1960's, with help of Canada, construction PHWR was started in Rawatbhata, Rajasthan. All important designs and components were supplied by Canada, but construction, installation and commissioning was done by India. Later due to Pokhran test Canada withdrew its support. This resulted in faster development of indigenous capabilities.
'Fast Breeder Test Reactor' is in operation at Indira Gandhi Centre For atomic Research, Kalpakam since 1985. It has provided valuable experience to our scientists and researchers all this while. Significantly, almost all the components, processes, fuel mixtures etc. deployed here are Indigenous, demonstrating capacity of our R&D facilities. BHAVINI has built a prototype Fast breeder Reactor with capacity of 500 Mw which is expected to go critical soon.
There are 21 plants in operation which constitute about 2.5% of total Installed electricity capacity of 223 GW. Indian Energy Policy envisages increase nuclear capacity to 20 GW by 2020 and 63 GW by 2032. To achieve this, large nuclear reactors such a Kudankulam 1, having 1000 MW are being established. This plant has Voda-Voda Energo Reactor.
In 2010 , NPCIL entered in MOU with French company AREVA for supply of Evolutionary Pressurized Reactors. These are 3rd generation pressurized water reactor and expected to be more efficient and economical. These Reactors are yet to start production anywhere in the world. Location of the project is at Jaitapur, Maharashtra and it will comprise units of 1650 MW, summing to 9.9 GW plant. Under MOU AREVA will undertake to operate the plant and there are disagreements over price of power supplied. DAE has expressed Rs 6.50/ unit us upper limit for power on the rational that by 2019 coal generated power will cost around Rs 6.20/ unit.
Another big upcoming plant under NPCIL is one at Srikakulam, Andhra Pradesh. It will operate Light Water Reactor and its capacity will be nearly 9500 MW ( 6 nuclear reactors).
India's Nuclear Deals
Indo US Nuclear – It was landmark deal, signed in 2008, which resulted in end of India's isolation for civil nuclear technology and supply nuclear fuel. After 1972's Pokhran tests, there were sanctions on India which prohibited all countries to supply anything for India's nuclear program.
But it placed India's civil nuclear installations under watch of International Atomic Energy agency subject to India's ratification of 'Additional protocol' which it did recently. Under this agreement US expected to supply India nuclear Reactors. US nuclear corporate lobby was decisive force behind this agreement.
Consequently, there was 'India specific waiver' by Nuclear Supplier's Group, which was vehemently opposed by China. Now India is only country outside NSG's 5 member (US, UK, China, France & Russia) who possess nuclear weapon but is allowed to trade in Civil Nuclear Materials. (Japan & Germany are non-nuclear powers as they enjoy US umbrella)
Similar deals were entered in with France, South Korea and latest with Australia.
But other contentious issue has been of Civil Nuclear Liability Act of India. It originally held that on accident operator (which as of now will be NPCIL) has liability up to Rs 500 crores and rest will be paid by government. This provision has significance only if government intends to privatize Nuclear Plant operations.